Passive Fire Protection Solution Projects
Apache North Sea Production Ltd.
Platform:
Beryl Alpha
Work Scope:
BSV were asked to manufacture, supply and install two off bulkhead weather seals for where the air inlet and exhaust ducts penetrate through the module bulkhead wall where the Gas Turbine is housed. Due to the age of the platform the weather seals both contained ACM’s, this work was classed as notifiable non-licensed and BSV worked with a specialist contractor to remove these seals, BSV then fitted new weather seals.
BP
Platform:
ETAP
Work Scope:
Installation of a double Firetex module seal (Fire rating A60) around opposing doorway frames linking existing module to new living quarters.
BSV led the installation team and were assisted by a representative from Amec Foster Wheeler.
Installation was completed on time and within budget.
CNR International
Platform:
Tiffany and Ninian Platforms
Work Scope:
Removal and installation of a number of fire seals on all platforms.
Our expertise in this area led to us leading a programme of work where we are replacing the majority of seals on all platforms.
Total E&P
Platform:
Elgin PUQ
Work Scope:
Removal and installation of most fire seals on Elgin.
This work scope was completed in three phases – removal, inspection and remediation and finally installation.
Repsol Sinopec Resources UK Ltd
Platform:
Clyde Platform
Work Scope:
As part of the 2018 TAR BSV were asked to change out 3 off A0 Bulkhead Wall.
Penetration Fire Seals where the Gas Turbine exhausts exits the Module Bulkhead wall.
BSV also fitted high temperature bellow wraps to protect the new seals from exhaust gas escaping through blown expansion joints adjacent to the seals.